GET BREAKING NEWS IN YOUR BROWSER. CLICK HERE TO TURN ON NOTIFICATIONS.

X

Interstate 70 expansion in Denver faces likely delay, contractor says

Kiewit and CDOT predict agreement soon over railroad bridge design

Work continues on the Central 70 project at Columbine Street on June 12, 2019. Now finished, the Columbine bridge across the future sunken I-70 lanes was constructed at ground level, before crews excavate beneath it.
PUBLISHED: | UPDATED:

Delays stretching nine months beyond the original schedule are now expected on the $1.2 billion Interstate 70 expansion in Denver, according to a recent document filed by the construction team — making it the latest big public project to run into a hiccup.

Kiewit-Meridiam Partners projected a nearly three-month delay to the “substantial completion” of the project in its most recent update for bondholders, in large part because of drawn-out discussions with Union Pacific Railroad over the design of a new railroad bridge. That would come on top of a six-month delay approved earlier this year by a Colorado Department of Transportation affiliate as part of a reshuffling of some project deadlines.

The upshot: The completion of major work on the project, originally set for March 2022, is now projected by KMP for December 2022. Finishing touches potentially would stretch into early 2023.

Though Central 70 project officials say they hope to win Union Pacific’s sign-off on the final bridge design in mid-September — and will work to rein in the delays — the setback has grown through the summer.

KMP’s latest monthly progress report, filed Aug. 29 in a public bond disclosure system, suggested more delays were possible. It said KMP’s delay projections didn’t account yet for the full impact of the railroad issue.

The issue raises the specter of a problem on another public-private partnership less than a month after Denver International Airport terminated its $1.8 billion contract with Great Hall Partners for the troubled terminal renovation project.

But for now, CDOT and Kiewit Infrastructure Co., the construction lead on Central 70’s $2.2 billion, 30-year-plus deal, say they have a good working relationship.

Project director Keith Stefanik characterized the railroad bridge design dispute as “a little hiccup.”

Yet talks among Union Pacific, CDOT’s project managers and the contractors have dragged on for at least three months longer than Stefanik said he expected, and Kiewit began noting the slowness of the progress as early as February.

KMP’s most recent report, which covered July activities, said about the bridge design that “communication has been systematically frustrated by, among other things, UPRR’s failure to appoint an authorized contact, UPRR’s refusal to cooperate, UPRR’s refusal to communicate with (Kiewit), and UPRR adding previously-unspecified requirements and criteria.”

The Omaha-based railroad responded Friday by pointing to the complexity of the structure and industry standards.

“From our perspective, a railroad bridge is much different from a highway bridge, and we have very specific guidelines that have to be met to ensure safety — not only for the trains but also for the motoring public,” spokesperson Kristen South said. “We are doing everything we can to be a good partner on this project.”

A rendering from a Central 70 project presentation shows the view from the completed “lowered section” that will replace a raised viaduct east of Brighton Boulevard. The planned Union Pacific Railroad bridge is visible above the highway.

Key bridge for project and freight line

The new bridge will replace an old one on Union Pacific’s busy main line that is key to its freight operations in Denver and the region. It crosses the most complex portion of the I-70 project, between Brighton and Colorado boulevards. The existing I-70 viaduct will be razed and replaced with a sunken, mostly open-air section of freeway that can accommodate planned new express lanes.

Paying for the new bridge and other work needed by Union Pacific was wrapped into the Central 70 project, and CDOT inked an agreement with Union Pacific to cooperate.

Stefanik and Kiewit’s Matt Sanman said design discussions with Union Pacific have taken a more productive turn in the last month or so.

CDOT’s project team last week was finishing up the latest design proposal for Union Pacific after receiving the railroad’s latest batch of comments in mid-August. South said the railroad sped up its review process to provide that response faster than usual.

“We are addressing those and we plan to resubmit the 100% drawings” by Monday, Stefanik said. “We anticipate that will address all of their comments.”

He characterized the disputes between Kiewit and Union Pacific as differences of interpretation in various design guidelines.

While awaiting Union Pacific’s design approval, Kiewit has forged ahead with prep work, and temporary “shoo-fly” bridges are in use. Kiewit also has pre-ordered steel girders that take about nine months to fabricate.

“Right now we’re in a pretty positive place with (Union Pacific),” Sanman said.

Kiewit’s report says most other activities along the 10-mile construction corridor have kept on schedule so far, though some were lagging in the central segment east of Colorado Boulevard.

Bridge is first of many dominoes

Central 70’s phases were set up like a carefully arranged set of dominoes, with completion of certain work necessary before other stages could begin. Project documents portray the design of the new Union Pacific bridge as the first step on the “critical path” of the project — delay that, and the result is more delays for all phases after it.

Under KMP’s public-private partnership deal, the contracting team must absorb any extra costs unless CDOT agrees to increase the project budget. So far, CDOT has rejected KMP’s compensation claims related to the rail bridge design delays.

Sanman declined to comment on the additional expected costs.

But CDOT did agree to kick in $7.6 million to settle earlier project claims by KMP, including some that stemmed from other matters involving Union Pacific. That May agreement resulted in the shuffling of later project deadlines, keeping most major work on the same schedule while allowing final paving and some other activities to happen later, in warmer months better suited for them. It also increased the number of project payment milestones from four to six.

The revised baseline schedule still would have placed eastbound traffic in its final configuration in the new sunken lanes by March 2022, but that’s now in doubt. Kiewit’s latest report forecasts that will happen five months later, in August 2022.

Both Kiewit and the project director predict they can reduce the delays, however.

“We have three more construction seasons here, so we still have a long time to be a little more efficient and figure out things out,” Stefanik said. “I think we have plenty of time to make up any lost time with this (bridge) approval. … Hopefully once we get the design approval, we’ll start seeing improvements in the schedule.”


Central 70 project original scheduleThe original plan for the Central 70 project, as shown in the graphic, called for substantial completion of the major work in March 2022. That milestone recently was adjusted to September 2022, but the contracting team now projects it will be reached in December 2022.

(Click to enlarge)


blog comments powered by Disqus